Product · Line equipment

Line equipment — crushing, screening, drying, cooling, conveying and packing

Five stages sized off the main kiln. The kiln sets the iodine value; these five decide whether the plant actually reaches its rated tonnage.

Stages
5
Line match
0.5–3t/h
Sizing margin
1.2–1.5×
Reply within 24h · mass balance included · no obligation
Discharge cooler and conveying section of an activated carbon line
HL series · Henan, ChinaHL SERIES
180+lines supplied0.5–3 t/hfinished carbon, five models15–25 don-site commissioning2 yrmechanical warrantyEngineer-written answers, not sales copy

Key specifications

Reference configuration for a 1 t/h finished-carbon line.
StageEquipment and size
Main line1.0 t/h finished carbon (coconut shell, 1,000–1,050 mg/g)
CrushingHammer or roll crusher, 6–8 t/h of raw shell
ScreeningTwo-deck trommel, 3–12 mm product, 8–10 t/h
DryingRotary dryer Φ1.5 × 12 m, 6–7 t/h, 18% → 8% moisture
CoolingRotary cooler Φ1.2 × 8 m, 1.2 t/h, discharge ≤ 60 °C
ConveyingDrag chain + bucket elevator, ≤ 200 °C, water-jacketed on hot sections
Packing25 kg semi-automatic, 2–3 bags/min, ±0.5% accuracy
Dust extraction4,000–6,000 m³/h at crushing and screening; 2,000–4,000 m³/h at packing
Installed power55–75 kW for the auxiliary set
Delivery60–90 days, shipped to site with the main kiln on one layout

The kiln sets iodine value; the auxiliaries set output

Nobody gets this wrong about the kiln itself. But when a plant rated at 2 t/h settles at 1.6 t/h, the cause is almost always at one of the two ends: feed that was never screened properly going in, or carbon that never cooled down coming out. Neither appears on the main equipment quotation.

That is why we size the five stages on the same layout drawing as the kiln instead of leaving the customer to source them separately. Screening capacity, dryer evaporation, cooling area and packing rate are all back-calculated from the main line's hourly output, with 20–50% headroom — not caution, but because feed moisture, particle size and season will consume part of it.

Sized for 1, 2 and 3 t/h lines

Standard ranges; add margin on the relevant stage when feed is wet, wide in size distribution, or the product is fine.
Stage1 t/h line2 t/h line3 t/h line
Crushing (raw shell)6–8 t/h11–13 t/h16–18 t/h
Screening8–10 t/h, two decks14–17 t/h, two decks20–24 t/h, three decks
DryingΦ1.5 × 12 mΦ1.8 × 14 mΦ2.2 × 16 m
CoolingΦ1.2 × 8 mΦ1.5 × 10 mΦ1.8 × 12 m
Packing2–3 bags/min, semi-auto3–4 bags/min4–6 bags/min, twin station
Auxiliary installed power55–75 kW95–120 kW140–180 kW

What each stage is for

Crushing and screening

Shell is crushed to the target size and split on a trommel or vibrating screen into 3–12 mm kiln feed and sub-3 mm fines. This is the stage most often trimmed: an undersized screen, or none at all, compacts a shaft furnace bed until the gas short-circuits, or blows fines straight into the rotary kiln's off-gas. Fines have to leave the circuit here; downstream they are pure loss.

Drying

A rotary dryer takes shell from 12–18% moisture down to below 8%. Heat comes from the waste-heat boiler or afterburner flue gas at 300–400 °C, so no extra fuel is burned. Skipping this stage costs 10–15% of carbonization capacity, because the kiln's heat goes into boiling water instead of pyrolysis.

Cooling

Hot carbon leaving the kiln must reach below 60 °C in a water jacket or rotary cooler before it touches a belt. Above 120 °C it oxidises on the conveyor and the last 20–30 mg/g of iodine value disappears. Wet-season feed makes it worse. This is the stage most often sized from the paper rating rather than the real duty.

Conveying

Drag chains, bucket elevators and belts selected per temperature and abrasiveness: water-jacketed or heat-resistant on hot sections, standard belt after cooling. Enclosure and dust extraction go in together — activated carbon dust is both abrasive and conductive, and it finds motor terminals and switchgear.

Packing and dust extraction

25 kg bags, 500 kg bulk bags or loose. Weighing at ±0.5%, with de-aeration and compaction for bulk bags. Dust extraction at the packing head is not cosmetic: it decides whether the plant passes an environmental inspection, and whether anyone will work a full shift there.

The two places where saving money costs more

Screening first. Screens are cheap, so they are the first line item cut. But feed with more than 15% below 3 mm will not reach rated iodine value in a shaft furnace, and in a rotary kiln it shows up as dust loading and rapid fouling in the waste-heat boiler. Two decks and quick-change mesh cost far less at build stage than a second screen later.

Cooling second. A cooler sized on nominal conditions runs out of capacity in the wet season. On the 3 t/h palm kernel shell plant in Kalimantan the cooler was designed for the same 80 °C discharge, but it was sized on nominal conditions with no margin, and in the wet season it delivered carbon to screening at 90–110 °C — above the point where fines begin to oxidise. Lengthening the cooling section by four metres brought discharge to 55–65 °C with no extra water and stabilised the iodine value. That change cost far less than a year of lost iodine value.

Auxiliary stages in three delivered projects

Only the equipment-related part is listed here; kiln and process data sit on the case pages.
ProjectAuxiliary scopeWhat happened on site
2 t/h coconut shell line, Sumatra60 t homogenising silo with blending screw; discharge cooler sized at 2 t/h, 80 °C outletChar from four suppliers ranged 780–1,020 mg/g iodine potential and was blended before the kiln; in the wet season discharge ran 110–120 °C and cooling became the bottleneck
3 t/h palm kernel shell plant, KalimantanCooling section lengthened by 4 m; waste-heat boiler tied into the dryerDischarge held at 55–65 °C; waste heat covered 46% of plant steam, net fuel 38% below estimate
1 t/h hazelnut shell line, TürkiyeCrushing and screening switched by seasonal batch; 25 kg semi-automatic packing14.8% overall yield, 590 t in the first year, run in 6–8 week campaigns

Supply and delivery

  • Any single stage can be supplied on its own or as part of a complete line — quoted separately either way.
  • One layout drawing with the main kiln: interface elevations, chute angles and dust pick-up points defined once.
  • Electrical and control in the same PLC cabinet, so no interlock gap between kiln supplier and equipment supplier.
  • Commissioning once, with the performance test run as a 72-hour continuous line test.
  • Wear parts (screen mesh, hammers, drag flights, belts) shipped with the machine, with replacement intervals stated.

Size from one number only: the line's hourly output

Do not size from a supplier's nominal throughput. Two screens both rated 10 t/h will differ by 30% in effective capacity between coconut shell and palm kernel shell. Give bulk density, moisture and size distribution, and let the equipment be back-calculated on effective capacity. Withhold one of those numbers and the margin becomes a guess — usually in the wrong direction.

Questions buyers ask before ordering

Straight answers with numbers. If yours is missing, send it over.

Can I buy just one stage?
Yes — crushing and screening and discharge coolers are the most common single-machine orders. One condition: the interfaces have to be re-checked against your kiln — chute angles, elevations, dust points, electrical interlocks. We price interface verification as a line item rather than shipping a machine and leaving the connection to you.
Hammer crusher or roll crusher?
For brittle shell such as coconut or hazelnut, a hammer mill is efficient and adjustable but produces 5–8% fines. Palm kernel shell is tougher, so rolls or toothed rolls generate less powder. If you can sell the sub-3 mm fraction as powder carbon, hammers are fine; if fines are pure loss, rolls pay back.
How long does the cooler need to be?
Driven by hourly output and feed moisture, not by kiln length. Rule of thumb: Φ1.2 × 8 m at 1 t/h, Φ1.5 × 10 m at 2 t/h, Φ1.8 × 12 m at 3 t/h, and add 2–4 m to each step where moisture is above 12% year round. Longer is safer — a discharge below 60 °C matters more than the extra steel.
How is dust extraction capacity set?
Point by point, not by floor area: 4,000–6,000 m³/h at crushing and screening, 2,000–4,000 m³/h at packing, 1,500–2,500 m³/h at each transfer point. Too little and dust escapes; too much and you pull the fine product into the bags while wearing out the filter. Carbon dust is conductive, so keep the filter and the switchgear apart.
What changes on a powder carbon line?
Three stages: screening becomes multi-deck fine screening to the target mesh, conveying moves to enclosed pneumatic or tubular chain conveyors, and packing switches to valve bags with de-aeration. Cooling can actually be simplified because powder sheds heat quickly. Dust extraction capacity goes up 30–50% overall, because a powder line has far more dust points than a granular one.
Sizing a line? Start with the mass balance.

Send the raw material, target tonnage and finished spec. You get a configuration, a utility schedule and a budget range — not a brochure.