Capacity · 2 t/h

2 t/h activated carbon line — 48 t/day, layout, utilities and budget

The sweet spot for a plant selling into water treatment at scale: one kiln, one crew, 48 tonnes a day, and a steam demand most sites can cover with a single boiler.

Output
48t/day
Steam
3.2t/h
Budget
620–820k USD
Reply within 24h · mass balance included · no obligation
2 t/h activation line with discharge cooling and conveying
HL series · Henan, ChinaLINE LAYOUT
180+lines supplied0.5–3 t/hfinished carbon, five models15–25 don-site commissioning2 yrmechanical warrantyEngineer-written answers, not sales copy

Key specifications

Activation section. Carbonization and drying add roughly 40% to footprint and cost.
ItemRequirement
Finished output2.0 t/h · 48 t/day
Char feed3.3–3.5 t/h
Steam3.2 t/h at 0.8 MPa
FuelNatural gas 240–300 Nm³/h
Installed power110 kW
Cooling water22 m³/h
Footprint, activation section28 × 11 m
Footprint, with carbonization42 × 16 m
Operators4 per shift, 3 shifts
Delivery100–130 days

Why 2 t/h is the usual answer above 30 t/day

Below 30 t/day, the arithmetic usually favours a 1 t/h unit running two shifts. Above 45 t/day, most buyers are choosing between one 2 t/h kiln and two 1 t/h kilns, and the single larger unit wins on almost every measure: one lining to maintain instead of two, one control system, one crew of four instead of six, and about 12% lower fuel per tonne because the shell-to-surface ratio improves.

The constraint is utilities. A 2 t/h line wants 3.2 t/h of steam, which means a 4 t/h boiler with normal margin, and 110 kW of connected load, which sits comfortably on a 315 kVA transformer. Sites that cannot reach those numbers should stay at 1 t/h rather than derate the kiln — a 2 t/h shell run at 1.2 t/h gives worse temperature uniformity than a correctly sized 1 t/h unit.

1 t/h versus 2 t/h, side by side

Same process, different scale economics. Figures are typical, not quoted.
Measure1 t/h2 t/h
Output24 t/day48 t/day
Equipment costUSD 380–520kUSD 620–820k
Cost per daily tonneUSD 15,800–21,700USD 12,900–17,100
Footprint24 × 10 m28 × 11 m
Operators3 per shift4 per shift
Steam demand1.8 t/h3.2 t/h
Installed power75 kW110 kW
Fuel per tonneBaselineAbout 12% lower

Site requirements that catch people out

  • Clear height of 10 m at the kiln position — a 2 t/h shell is longer and needs more crane room during lining work.
  • A concrete slab rated for 45 t static load with isolated footings; the drive end carries the torque reaction.
  • Steam header sized at 100 mm, not 80 mm, or pressure at the kiln inlet drops under load.
  • Truck access wide enough for a 40-foot container plus a 25 t crane, or the shell cannot be delivered.

Questions buyers ask before ordering

Straight answers with numbers. If yours is missing, send it over.

What does a 2 t/h activated carbon plant cost?
USD 620,000–820,000 FOB China for the activation section, or USD 900,000–1,150,000 with carbonization, drying and packing. Installed cost on an existing industrial site typically lands 18–22% above equipment value.
How much raw material does it consume?
3.35 t/h of char, or about 11.2 t/h of coconut shell if you carbonize on site at a 30% yield. Over 300 days that is roughly 80,000 tonnes of shell a year, which is why most 2 t/h plants buy charcoal rather than shell.
Can one supervisor run both the kiln and the boiler?
In many jurisdictions yes, if the boiler is automatic and the kiln has trend alarms. Budget four operators per shift: one on feed and discharge, one on the boiler and steam system, one on quality sampling and packing, one relief.
Is a waste-heat boiler worth adding?
At 2 t/h, yes in most cases. Off-gas at 500–700 °C can raise 1.2–1.6 t/h of steam, covering 40–50% of the kiln's own demand. Payback is typically 18–30 months at current gas prices.
Sizing a line? Start with the mass balance.

Send the raw material, target tonnage and finished spec. You get a configuration, a utility schedule and a budget range — not a brochure.