Capacity · 3 t/h

3 t/h activated carbon line — 72 t/day, layout, utilities and budget

Our largest standard model. At this size the kiln is no longer the hard part — steam, cooling and material handling are.

Output
72t/day
Steam
4.8t/h
Budget
880–1,150k USD
Reply within 24h · mass balance included · no obligation
3 t/h activation plant with waste-heat boiler and off-gas train
HL series · Henan, ChinaLINE LAYOUT
180+lines supplied0.5–3 t/hfinished carbon, five models15–25 don-site commissioning2 yrmechanical warrantyEngineer-written answers, not sales copy

Key specifications

Activation section at design load. A waste-heat boiler is included in the recommended scope at this size.
ItemRequirement
Finished output3.0 t/h · 72 t/day
Char feed5.0–5.2 t/h
Steam4.8 t/h at 0.8 MPa
FuelNatural gas 340–420 Nm³/h before heat recovery
Installed power160 kW
Cooling water32 m³/h
Footprint, activation section34 × 12 m
Footprint, with carbonization52 × 18 m
Operators5 per shift, 3 shifts
Delivery110–140 days

At 72 t/day, the furnace is rarely the bottleneck

Every project we quote at 3 t/h starts with the same question, and it is not about the kiln: where does 5 tonnes of char per hour come from, every hour, for 300 days? A 3 t/h line consumes roughly 36,000 tonnes of char a year, equivalent to 120,000 tonnes of coconut shell. Very few buyers have that supply chain, which is why large plants usually sit next to a char market or own carbonization capacity across several sites.

The second constraint is heat balance. Burning fuel for 4.8 t/h of steam plus kiln heat is the single largest operating cost. At this size we design the off-gas train with a waste-heat boiler as standard, recovering 2.0–2.6 t/h of steam and cutting purchased fuel by 40–50%. Projects that skip it usually retrofit within two years, at a higher price than including it from the start.

The third is cooling. 72 tonnes a day of carbon leaving the kiln at 900 °C carries a lot of heat, and an undersized water jacket shows up as iodine value loss at the discharge end, not as a temperature alarm.

Heat and mass balance at design load

Indicative figures for coconut shell char at 1,000 mg/g iodine value.
StreamFlowNote
Char in5.0 t/hDry basis, 2–12 mm
Steam in4.8 t/h0.8 MPa, superheated to 400 °C
Carbon out3.0 t/hCooled below 80 °C
Off-gasabout 18,000 Nm³/h500–700 °C at boiler inlet
Steam recovered2.0–2.6 t/hWaste-heat boiler
Net fuel demand180–250 Nm³/h gas equivalentAfter recovery

What changes in the plant design at this scale

  • Char storage with 72 hours of live capacity — at 5 t/h, a half-day interruption stops the kiln for a week of thermal recovery.
  • Two discharge lines running in parallel, so a conveyor fault does not stop the kiln.
  • Continuous iodine value sampling every 2 hours, not per shift; at 72 t/day a drifting batch is expensive.
  • Dedicated maintenance fitter on site, with a spare drive motor and one set of rabble or lifters held in stock.
  • Stack monitoring to local limits, since permitting thresholds are usually crossed between 2 and 3 t/h.

Permitting is the real lead time

At 3 t/h, environmental permitting commonly takes longer than manufacturing. Start the air-emission and wastewater application before you place the order, and confirm the stack height and monitoring requirements with the local authority — retrofitting a continuous emission monitor into a finished duct is far more expensive than designing it in.

Questions buyers ask before ordering

Straight answers with numbers. If yours is missing, send it over.

What does a 3 t/h activated carbon plant cost?
USD 880,000–1,150,000 FOB China for the activation section with waste-heat boiler, or USD 1.3–1.7 million for a complete line with carbonization, drying, washing and packing. Installed cost is typically 20–25% above equipment value at this scale because of civils and piping.
How much char does it need per year?
About 36,000 tonnes at 300 operating days, or 120,000 tonnes of coconut shell equivalent. Securing that supply is the real project risk — we will run the mass balance with you before quoting a furnace you cannot feed.
Can two 1.5 t/h units be better than one 3 t/h?
Only if you need redundancy or your char arrives from several locations. Two units cost 10–15% more, need two crews and two linings, but let you keep producing during maintenance. For a single-site plant with reliable char, one 3 t/h unit is the better investment.
What steam pressure should the boiler deliver?
0.8 MPa at the kiln inlet after superheat to 400 °C. Size the boiler at 6 t/h to cover kiln demand plus margin; a 5 t/h boiler will run at its limit and pressure will sag during feed surges.
Sizing a line? Start with the mass balance.

Send the raw material, target tonnage and finished spec. You get a configuration, a utility schedule and a budget range — not a brochure.